Completed using MICON’s German-engineered RVDS directional drilling technology, the achievement brought together technical expertise, specialised equipment and collaborative teamwork between BHP Carrapateena, PYBAR and specialist supply partners, MICON and Transco, to successfully deliver a hole of almost a kilometre in depth.
The project was not without its challenges, but the teams continued to work together to find solutions and achieve the required outcome.
Following breakthrough, BHP recognised the significance of the milestone and of drilling a hole of this length with minimal deviation. A fantastic achievement for everyone involved, and a great example of what can be achieved when client, contractor, technology partners and suppliers work together as a team.