Costerfield – 2014
Location: Central VIC
Client: Mandalay Resources
Commodity: Gold
SCOPE
- Independent development of the 4800 decline including drilling and blasting, load and haul, installation of ground support and mine services
- Requirement that all underground equipment must access through a 2.7m maximum height.
CONTRACT TYPE
- Schedule of Rates.
PROJECT STATISTICS
- Project Term: 6.5 months
- Employees: 27
- 1220m of development
- 80,000 tonnes of waste.
KEY PROJECT OUTCOMES
- Start-up and mobilisation completed within five weeks of tender award
- Development performance above client expectations
- Project to completion LTI free.
KEY MILESTONES
- Project commencement April 2014
- Project forecast completion September 2014
- Additional works for ventilation raises awarded to PYBAR.
KEY PLANT & EQUIPMENT
- 1 x Jumbo – Sandvik DD420-60
- 1 x Loader – Cat 1700G
- 1 x Truck – Cat AD40
- 1 x Telehandler – Manitou MT1030
- 1 x Integrated tool carrier – Volvo L90