Costerfield – 2015

Posted · Add Comment

Costerfield – 2015

Location
Central VIC
Client
Mandalay Resources
Commodity
Gold

SCOPE 

  • Independent development of the 4800 decline including drilling and blasting, load and haul, installation of ground support and mine services; and
  • Requirement that all underground equipment must access through a 2.7m maximum height.

CONTRACT TYPE

  • Schedule of Rates.

PROJECT STATISTICS

  • Project Term: 6.5 months;
  • Employees: 27;
  • 1220m of development; and
  • 80,000 tonnes of waste.

KEY PROJECT OUTCOMES

  • Start-up and mobilisation completed within five weeks of tender award;
  • Development performance above client expectations; and
  • Project to completion LTI free.

KEY MILESTONES

  • Project commencement April 2014;
  • Project forecast completion September 2014; and
  • Additional works for ventilation raises awarded to PYBAR.

KEY PLANT & EQUIPMENT

  • 1 x Jumbo – Sandvik DD420-60;
  • 1 x Loader – Cat 1700G;
  • 1 x Truck – Cat AD40;
  • 1 x Telehandler – Manitou MT1030; and
  • 1 x Integrated tool carrier – Volvo L90. 

Comments are closed.

 

Newsletter Signup

  • This field is for validation purposes and should be left unchanged.
 

Do not remove this

NEWSLETTER SIGNUP

  • This field is for validation purposes and should be left unchanged.
Website By: 121 Group