Deep South – 2015
Location: 170km North East of Kalgoorlie, WA
Client: Saracen Mineral Holdings
Commodity: Gold
SCOPE
- Mine development, mine production, production drilling, raise boring and cable bolting
- Narrow vein sub level stoping
- 500 metres of lateral development & 35,000 stope ore tonnes per month
- Supply labour, plant and material to establish greenfield underground site including site establishment, portal development, underground development and production
- The mine will access the ore body from the existing open pit using typical jumbo decline development and recover ore using traditional longhole open stoping methods
- Predominantly the decline and ore drives were mined using twin boom jumbos, with typical dimensions of 5.0mH x 5.0mW ore drives and larger capital development (5.5m W x 5.7m H)
CONTRACT TYPE
- Schedule of Rates
PROJECT STATISTICS
- Project term: 24 months
- Employees: 90
KEY PROJECT OUTCOMES
- First portal cut fired on 23 October 2015
- Commenced portal works September 2015
- 8.4km of advance
- 82,000 production drill metres
- 350,000t of ore mined
- 1,987,000tkm hauled
KEY PLANT & EQUIPMENT
- 2 x jumbos – Sandvik DD420-60 and Sandvik DD421-60C – TFX10/16
- 1x production drill – Atlas Copco E7C
- 1x charger – Normet Charmec 1610B
- 3x loaders – 3 x Cat R2900G – 1 Teleremote Guidance
- 3x trucks – 2 x Cat AD55B , 1 x Cat AD60
- 3x service – Volvo L120F IT, Volvo L120E IT – Open cab and Volvo L90C IT
- 1x raise bore – Atlas Copco Easer