Endeavor – 2006

Posted · Add Comment

Endeavor – 2006

Location
Cobar, NSW
Client
CBH Resources
Commodity
Zinc/Lead/Silver

SCOPE

  • Initial scope was more than 2,500 metres of upper decline development;
  • On successful completion of initial scope work continued with ongoing capital development throughout the Endeavor mine; and
  • This scope included a 6 month campaign of longhole production drilling.

CONTRACT TYPE

  • Fixed plant ownership and part of the workforce, balance of labour and variable plant costs were included in a cost/metre rate; and
  • The contract included payment of margin linked to KPIs consisting of proactive safety, quality and productivity measures.

PROJECT STATISTICS

  • Project Term: 14 months;
  • Employees: 76;
  • 2500m upper decline development;
  • On-going capital development and
  • 6 month campaign of longhole production drilling.

KEY PROJECT OUTCOMES

  • 600m of the development was completed using a Mitsui S200 roadheader;
  • Built productive integrated team of client & PYBAR employees;
  • Successfully utilised existing client equipment with integrated team; and
  • On time & on budget, achieving targeted margin aligned to KPIs of proactive safety, quality and productivity.

KEY MILESTONES

  • Project commenced: April 2007
  • Project completed: June 2008

KEY PLANT & EQUIPMENT

  • 2 x Jumbos – Tamrock Axera D07;
  • 1 x Truck – Cat AE40;
  • 3 x Loaders – Volvo L50D; and
  • 1 x Charge up Unit – Normet 1610B.

Comments are closed.

 

Newsletter Signup

  • This field is for validation purposes and should be left unchanged.
 

Do not remove this

NEWSLETTER SIGNUP

  • This field is for validation purposes and should be left unchanged.
Website By: 121 Group