Matilda – 2016

Posted · Add Comment

Matilda – 2016

Location
Wiluna, WA
Client
Blackham Resources Limited
Commodity
Gold

SCOPE

  • Mine development and stoping

CONTRACT TYPE

  • Schedule of rates

PROJECT STATISTICS

  • Employees: 107

KEY PROJECT OUTCOMES 

  • Commenced Development in August 2016;
  • 9 km of advance;
  • 5,000 production drill metres;
  • 48,000 t of ore mined; and
  • 951,000tkm’s hauled. 

KEY PLANT & EQUIPMENT (at peak)

  • 3 x Jumbos – Sandvik DD420-60 -TFX 8/14, Sandvik 7-260  – TFX 8/14 and Sandvik DD310 single boom – TFX 6/121 x Loader;
  • 1x Production drill – Sandvik Solo 7-7V;
  • 1 x Charging – Normet Charmec 1610B
  • 3 x Loaders – 2 x CAT R1700G and 1 x CAT R1300G;
  • 3 x Trucks – Cat AD45B;
  • 3x Service – Volvo L120F IT, Volvo L90E IT and ZEUS 33.11TA EWP Telehandler; and
  • 1x Grader – Cat 12H. 

Comments are closed.

 

Newsletter Signup

  • This field is for validation purposes and should be left unchanged.
 

Do not remove this

NEWSLETTER SIGNUP

  • This field is for validation purposes and should be left unchanged.
Website By: 121 Group