Thalanga – Far West – 2018
Location: Queensland
Client: Red River Resources
Commodity: Zinc
SCOPE
- Box cut excavation of Far West portal via drill and blast methods managing a two subcontractor
- Ground support of box cut with shotcrete and jumbo with PYBAR employees and equipment
CONTRACT TYPE
- Fixed and variable
PROJECT STATISTICS
- Project Term: 1-2 Months
- Employees: <16 people
KEY MILESTONES (to date)
- Firing of the box cut completed on 16 May
KEY PLANT & EQUIPMENT
- Drill Rig – Atlas Copco 600 Mk4 Blashole rig
- Moxy truck
- Shotcrete machine
- Explosives truck
- Dozer
- Jumbo (utilise drill from Thalanga West 45 project)