Vivien Gold Mine – 2015
Location: Leinster, WA
Client: Ramelius Resources
Commodity: Gold
SCOPE
- Mine Development and Stoping provide all mining services to complete the mining cycle.
CONTRACT TYPE
- Schedule of rates
PROJECT STATISTICS
- Project term: 52 months
- Employees: 55
KEY PROJECT OUTCOMES
- Commenced work in pit for portal: May 2015;
- 12.1 km of development;
- 159,000 production drill metres;
- 777,000 tonne of ore mined; and
- 2,500,000 tonne km’s hauled.
KEY PLANT & EQUIPMENT
- 1 x Jumbo – Sandvik DD421-60 – TFX 8/14;
- 3 x Loaders – 1 x Cat R2900G, 2 x Cat R1700G – 1 with Teleremote guidance;
- 2 x Trucks – Cat AD45B;
- 1 x Production Drill – Sandvik Solo DL430-7C;
- 1 x Charging – Normet Charmec 1614B;
- 1 x Service – Volvo L120F IT and Volvo L90E IT; and
- 1 x Grader – Cat 140H.