Lihir Gold – 2011
Location: Ballarat, VIC
Client: Ballarat Gold Mine
Commodity: Gold
SCOPE
- Underground waste development at the Ballarat mine.
CONTRACT TYPE
- Schedule of rates.
PROJECT STATISTICS
- Project Term: 10 months; and
- Employees: 50.
KEY PROJECT OUTCOME
- Delivered the project scope on time & on budget; and
- Met or exceeded the Clients KPI’s, outcomes and expectations.
KEY MILESTONES
- Project Commencement: March 2011; and
- Scheduled access to the first quartz reefs and for first gold production during quarter 3 of 2011.
KEY PLANT AND EQUIPMENT
- 1 x Jumbo – Tamrock Axera D07-260;
- 1 x Loader – Toro 1400;
- 2 x Trucks – 1 x Cat AD45B, 1 x Cat D25;
- 1 x Shotcreter – Roboshot Maxijet;
- 1 x Agitator Truck – JCB 714; and
- 1 x Integrated tool carrier loader – Volvo L120C.